Consultant on real estate development, redevelopment, capital finance and economic ... Instructor for ULI Real Estate School on development process, public -.
Fundamental Skills for Real Estate Development Professionals I Site Selection and Due Diligence October 17, 2012 Charles A. Long Charles A. Long Properties LLC 10:45 a.m. -12:00 p.m. Site Selection and Due Diligence

Topics we plan to cover I.

Risk management during site acquisition.

II. Maximum supported investment and residual land value III. Six focus areas of project management and due diligence. IV. Acquiring the site while conducting due diligence Site Selection and Due Diligence

Learning Objectives: For you to understand: 1. Risk management for site acquisition. 2. Determining price and terms for site acquisition. 3. Due diligence as part of site acquisition. Site Selection and Due Diligence

3

Our approach Overview with class discussion Ground rule: Ask questions as they occur to you.

Site Selection and Due Diligence

•Charles A. Long •Charles A. Long Properties, LLC •Oakland, CA

• Developer specializing mixed use development in California, US • Consultant on real estate development, redevelopment, capital finance and economic development • Instructor for ULI Real Estate School on development process, publicprivate partnerships and sustainable development • Former city manager of Fairfield, CA and interim manager in Mammoth Lakes, Pinole, and Hercules, California. • Author of “Finance for Real Estate Development” published April 2011 and contributing author to ULI Retail Handbook. • Served on 14 ULI advisory panels, chairing panels in Salem OR, Boise, ID and Dallas, TX • Masters in Public Policy, UC Berkeley; platoon sergeant, US Army

Site Selection and Due Diligence

5

Finance for Real Estate Development published by ULI April 2011

Site Selection and Due Diligence

Managing Risk in the Development Process

Site Selection and Due Diligence

Development today is more complicated physically and economically

Appleton Mills, Lowell, MA

Lakeside Steel Plant, Chicago

• More urban and mixed use • Entitlement is longer and riskier • More complicated economics • More conversions from old uses • Less leverage and no “value add” financing • Density confusion

West End Commons, Oakland, CA

Site Selection and Due Diligence

8

Mixed use challenges • Community acceptance • Resizing the infrastructure • Financing challenges • Getting the density right • Sector differences in market strength

Bitola, Macedonia

• Valuing income and for-sale • Federal pre-sale requirements for condo projects • Liability on for-sale residential • Conflicts among uses Portsmouth, New Hampshire

• Parking: costs, layout operations

Site Selection and Due Diligence

9

The Great Recession has changed the capital stack Equity Mezzanine or performing debt

Debt

Much higher equity: now 35% or more—recourse provisions tighter Disappearance of "Gap" financing to pay for “value-add” conversions

Much lower debt: now 65% or less

Site Selection and Due Diligence

Result of the changes to the capital stack: • Overall project returns must be higher to attract capital • Equity sources have more project control.

Site Selection and Due Diligence

Development is… a separate self financing enterprise that goes from small to large.

Site Selection and Due Diligence

•12

The Development Process has three phases

Site Selection and Due Diligence

“The developer is the conductor of a chaotic and multi-disciplinary process, albeit one that depends on exogenous forces, especially market demand and capital availability.” “No industry involves the collaborative effort of so many different disciplines to create a product in such a publicly accountable process as development.” Site Selection and Due Diligence

80% to 90% of project value is created in the pre-development phase Acquisition, design, entitlement, financing, risk management

Project Value Site Selection and Due Diligence

15

Pre-development work manages risk for all phases

By the start of construction, risks should be reduced to factors that have already been addressed and are controlled through good management.

Site Selection and Due Diligence

•16

Pre-development funds are at risk • Funding for pre-development comes primarily from developer capital. • If source is outside investors, required return at least 25% and higher. • Many projects are abandoned when information about costs, markets or government approval conditions show that the project is unviable.

Site Selection and Due Diligence

•17

5 Principles of successful development management 1. Invest in information wisely: More information reduces risk but it also has a cost. Is the risk of loss worth the reduction in risk? 2. Manage time: the longer it takes, the more expensive the process will be.

Site Selection and Due Diligence

•18

5 Principles of successful predevelopment management (continued) 3. Manage tasks: Identify and budget all tasks and monitor. 4. Anticipate: Things go wrong in the Development phase because somebody didn’t spend the money early enough, or somebody didn’t communicate key information. Things going wrong early are cheaper than later. Site Selection and Due Diligence

•19

5 Principles of successful predevelopment management (continued) 5. Foster teamwork among the professionals: Select an effective team of multi-disciplinary players. Especially, focus on the relationship between the architect and contractor. a) As much as 80% of project costs will be spent through the contractor, another 5% through the architect. These two disciplines MUST work together.

Site Selection and Due Diligence

•20

Six areas of project management Site conditions

Market and Marketing

Entitlement Financial Viability Analysis Construction cost management

Product type and project design

Site Selection and Due Diligence

Successful Developers ANTICIPATE! It is cheaper to solve problems earlier than later. Most of the value of a real estate project is created before you start construction. Site Selection and Due Diligence

Questions 1. 2. 3. 4.

Why does a real estate project have the greatest risk of losing money in the early phases? What are the 5 principles of pre-development management? What six areas do you need to focus on to reduce risk and create value in the pre-development phase? What do you need to have accomplished before you spend significant amounts of money on a real estate project?

Site Selection and Due Diligence

Project viability and residual land value

Site Selection and Due Diligence

24

Project return is expressed many different ways • Pre-tax Internal Rate of Return(IRR) – Leveraged – Unleveraged

• Net Present Value – Present Value of cash flow

• Net operating income/Total cash cost • Cash-on-cash • Return on sales (ROS) • Return on costs (ROC) • Return on equity (ROE)

Make sure you understand how project return is calculated! Site Selection and Due Diligence

•25

Internal Rate of Return shows the annual return of a cash flow series. Spreadsheets make it easy: Income for each period Initial Investment

-$100.00 7.63%

1

2

3

4

$6.00

$7.00

$8.00

$110.00

Internal Rate of Return

The discount rate at which the present value of the stream of income equals the amount of the investment. BUT, FOR IRR TO BE ACCURATE, THE PROJECTIONS MUST BE ACCURATE. Site Selection and Due Diligence

•26

Three elements to evaluate project viability: 1. Project Value: based on either total sales or on valuation of the stream of income 2. The Hurdle Rate: The minimum rate reflecting the cost of capital and time that the capital is used. 3. Project Costs: A valid estimate.

Site Selection and Due Diligence

27

A Project is “viable” if VALUE minus COSTS is sufficient to pay:

– Cost of Capital – Developer profit

Site Selection and Due Diligence

28

PROJECT VALUE BASED THE MARKET – For Sale Project: (primarily residential) Gross sales less marketing – Income projects (retail, office, apartments, etc.): INCOME DIVIDED BY A “CAP RATE”. Site Selection and Due Diligence

29

How to value an “income” project. • Income project produce annual income from rent, maintenance charges and other sources. • Apartments, offices, retail stores, business parks are all, usually, income projects. • The income after expenses is called “Net Operating Income” of NOI. It is the same as annual profit. • The market values the NOI using something called a “capitalization rate”. Site Selection and Due Diligence

•30

A capitalization rate is simply an shorthand indicator of market strength. Net Operating Income (NOI) Cap Rate= Project Value Project Value=

NOI Cap Rate

High cap rate indicates market weakness and low cap rate indicates market strength.

Site Selection and Due Diligence

•31

Cap rates reflect market sentiment

Site Selection and Due Diligence

Cap Rates reflect capital markets and sector differences

Site Selection and Due Diligence

•33

Cap Rates in many sectors are recovering (Apartment Cap Rate Trend)

•Source: REIS Sept 28, 2012 Site Selection and Due Diligence

Cap rate is the inverse of the P/E ratio used in the stock market Cap rate 2% 3% 4% 5% 6%

P/E Ratio 50 33 25 20 16.7

Site Selection and Due Diligence

•35

Some stock P/E ratios Average S&P stocks General Electric Microsoft Starbucks Whole Foods Mkt.

15.5 14.31 19.96 45.22 32.18

What does a high P/E (or low cap rate) signal about expectations of growth in income? Site Selection and Due Diligence

•36

Pop quiz 1 What is the project value? NOI

$3,000,000 $3,000,000 $2,000,000 $2,000,000

Cap Rate

5% 6% 4% 5%

Site Selection and Due Diligence

•37

Investment in real estate compared to investment in stocks

• A real estate project’s “stabilized” NOI is frequently perceived as more predictable than future earnings of a company. • Cap rates in 1990’s were 8% and up. • In 2000’s they dropped in some markets for some sectors below 5%. Site Selection and Due Diligence

•38

Web sites where you can obtain current market data • Real Estate Research Council www.rerc.com • Real Capital Analytics http://global.rcanalytics.com/ • National Council of Real Estate Investment Fiduciaries (NCREIF) http://www.ncreif.com • Reis: http://www.reis.com/index.cfm Site Selection and Due Diligence

Questions

1. What is happening with cap rates today? 2. Are they different for different regions? For different sectors? Why?

Site Selection and Due Diligence

•40

DETERMINING THE ROC HURDLE Cost of capital: blended cost of equity and debt over the time to construct.

Example

Cost of equity: 20% per year (30% of costs) = 6% Cost of debt:

5% per year (70% of costs) = 3.5%

TOTAL ANNUAL COST OF CAPITAL

= 9.5%

If a project takes 2 years to construct, cost of capital is: 9.5% per year or a total of about 20%. Site Selection and Due Diligence

Typical hurdle rates based on duration of development period 1-year: about 10% 2-years: about 20% 3-years: about 30%

Site Selection and Due Diligence

Hurdle rates for other capital structures and construction periods Debt

Equity

Months to achieve project value

% funding

36

75%

6.00%

36

80%

24

Interest

% funding

Annual return

Hurdle Rate

25%

20%

31%

6.00%

20%

20%

29%

75%

6.00%

25%

20%

20%

24

80%

6.00%

20%

20%

18%

12

80%

6.00%

20%

20%

9%

Site Selection and Due Diligence

The “hurdle rate” is the minimum return necessary for a project to be viable • Cash-on-cash hurdle rate: a shortcut to evaluate project viability • Detailed cash flow on each land acquisition opportunity is impractical and inaccurate • Use a the same cash-on-cash hurdle rate where you have projects that share the same financing and “product absorption” characteristics. • Once a property is tied up, and more information is available, do a more detailed IRR analysis. Site Selection and Due Diligence

•44

OK. Once you have Project Value and Hurdle Rate, then you can determine how much you can afford to spend on a project compared to what it is estimated to cost. Maximum supported investment

Project Value = 1 + hurdle rate

If estimated project costs exceed the Maximum Supported Investment then the project is not viable and the developer will abandon the project. Site Selection and Due Diligence

•45

A cash-on-cash return evaluates project viability based on estimates of cost and value • Be careful to include adequate cost allowances for all categories and, especially, contingency. • Use a cash-on-cash hurdle rate for projects with similar capital stacks and absorption profiles.

Site Selection and Due Diligence

46

Pop quiz 2 What is the maximum supported investment? Project Value

$36,000,000 $39,000,000 $50,000,000 $60,000,000

Hurdle Rate

20% 30% 25% 25%

Site Selection and Due Diligence

•47

Land price is usually the first cost that the developer determines. If the land price cannot be supported by the project, the developer should immediately abandon the project.

Site Selection and Due Diligence

•48

Residual Land Value is: The price the project can afford for land after all other costs of development. Obtaining site control by tying up the land is the first major decision a developer makes and is based on market and costs. If the costs of development change, the developer risks a loss because the land price has already been determined. Site Selection and Due Diligence

49

Residual land value is the land component of supported investment. Project Value

1 + hurdle rate

Supported investment

MINUS Costs without land =Residual land value

Site Selection and Due Diligence

50

Pop quiz 3 What is the project residual land value? Project Value

Project Cost (w/o land)

Hurdle Rate

$36,000,000 $39,000,000 $50,000,000 $60,000,000

$25,000,000 $25,000,000 $35,000,000 $43,000,000

20% 30% 25% 25%

Site Selection and Due Diligence

•51

Residual land value is what is left to afford Sale price of house #1: $500,000 $100,000 $25,000 $60,000 $65,000

Sale price of house #2: $500,000 Residual Land Value Agency requirements Profit Design, finance, management, marketing

$75,000 $50,000 $60,000 $65,000

$250,000

$250,000 Construction

Site Selection and Due Diligence

Land Value Changes with Use Example on 3 acres Scenario 1 80 townhomes net sales: $24 million costs (before land): $16,000,000. land value (20% hurdle): $4.0 million Site Selection and Due Diligence

53

Land Value Changes with Use Example on 3 acres Scenario 2: 210 apartments (podium) NOI: ($30/sf rent): $3.3 million. Project value: $65.5million (5% cap) costs (before land): $42 million. land value at (30% hurdle) $8.4 million Site Selection and Due Diligence

54

The return on a project pays: • Cost of debt: interest on a construction loan (4%-6%) • Return on equity: return to investors (15% to 20%) • Developer profit: based on project performance after paying costs of capital.

Site Selection and Due Diligence

Developer profit comes from: • Fees: Developer fee of 2-4% of cost with incentive bonuses. • Co-investment: Developer is an equity investor in 10-15% of equity requirement. • Sharing of success: – –

Participation in profits over the “preferred return” of 812% Higher participation in profits over a target of 15-18%.

Site Selection and Due Diligence

What happens to a project’s financial viability if: : and costly? • The entitlement is long • The public agency suddenly changes the development conditions? • The public agency’s development conditions are uncertain?

• The cost of development conditions causes total costs to exceed project value? Site Selection and Due Diligence

57

How should you adjust residual land value for: • • • •

Long and costly pre-development? Longer construction period? Higher market risk? High land deposit payments during predevelopment? • Higher city development fees?

• Land as “equity”? Site Selection and Due Diligence

58

Questions 1. Why is it important to determine land prices as early as possible? 2. What information do you need to determine whether land price is affordable by the project? 3. What challenges do you face in acquiring land? Site Selection and Due Diligence

The six focus areas of project management and due diligence

Site Selection and Due Diligence

60

Project Management • Development is a “team process”—create and foster a common vision. • Have a complete list of all tasks—Monitor! • Foster the architect/contractor relationship: Insure it is collaborative not confrontational. • Understand what components cost compared to their value.

Site Selection and Due Diligence

Shape the land acquisition terms to the information Site analysis

Market Community assessment Support

Project design

Financial analysis to acquire land at no more than its Residual Land Value Site Selection and Due Diligence

Construction costs

Perceived risk in each area will affect project return requirements Site Conditions

Project Design

• Environmental hazards • Surrounding uses

Market • • • •

Sector Volatility Location Region

• Constructability • Response to market

Construction • Inflationary conditions • Contractor Experience Site Selection and Due Diligence

Site analysis effects development potential and costs • Area and boundaries

• Evaluate— • Cost increases

• Ownership • Condition of title

• Ability to proceed

• Surrounding uses

• Before or after due diligence.

• Hazardous waste, poor soils or other special conditions?

• Insure conditions to close in PSA backstops

Site Selection and Due Diligence

The market determines what your project is worth • Total sales or • NOI valued at a cap rate

• The market now, NOT wishful thinking.

• Capital market conditions

• Anticipate the marketing strategy.

• Shape the unit mix, layout and amenities

• Verify with outside experts Site Selection and Due Diligence

Know the community (the entitlement process) • Approving authority • Regulatory structure

• Try to obtain commitments from the public agency.

• Stakeholder involvement

• Meet early with stakeholders.

• Cost of conditions

• Create ownership.

• Cost and time for processing Site Selection and Due Diligence

Project design responds to market, entitlement and cost. • Density, units, parking, access, circulation • Market analysis informs product design • Pay attention to density/cost tradeoffs

• More is not always more. • Understand cost and value.

Site Selection and Due Diligence

Construction costs • Estimate each cost category, do not lump! • Know the market for construction services. • Identify areas of uncertainty • Include a contingency

• Solve cost problems early • Foster relationship between architect and contractor.

• Involve the contractor in design. Site Selection and Due Diligence

Financial Analysis • No wishful thinking— VALIDATE!

• Use a valid hurdle

• Work to reduce uncertainty.

• Understand the economics of each component

• Include a contingency—higher at the beginning.

• You can’t cut the board longer.

• Update continuously! Site Selection and Due Diligence

Cost pro-forma includes: 1. Building costs 2. Site Development (demolition, grading, utilities and landscaping) 3. Parking (may be included in building for some types of projects) 4. Connection and impact fees 5. Offsite costs such as traffic signals or road improvements 6. Design (architecture, engineering, consultants, etc) 7. Marketing (brokers, advertising, etc.) 8. Construction management 9. Financing /legal/administrative 10. Taxes during construction

11.Contingency: 10-15% in early stages Site Selection and Due Diligence

DO NOT LUMP COSTS! UNDERSTAND COSTS AND VALUE! YOU CANNOT CUT THE BOARD LONGER! Site Selection and Due Diligence

The economics of density: More is sometimes less

Site Selection and Due Diligence

Why things go wrong • Somebody didn’t spend the money early enough. • Somebody didn’t communicate key information. • Things going wrong early are cheaper than later. • Control risk through due diligence and communication. The best way to solve a problem is to find out about it early enough to do something about it. Site Selection and Due Diligence

Questions

1. Why is development a team process?

Site Selection and Due Diligence

Acquiring the site

Site Selection and Due Diligence

75

The first six steps 1. Look for sites, investigate and identify those with promise. 2. Do the six part analysis on the promising sites and decide what the site is worth. 3. Begin negotiation with owners.

Site Selection and Due Diligence

The first six steps (continued) 4. Make the offer: Letter of intent (LOI) or letter offering to purchase. This step frequently goes on for a while. 5. Execute a purchase contract setting forth detailed terms of purchase and period of due diligence.

Site Selection and Due Diligence

The first six steps (continued)

6. Conduct the due diligence process prior to escrow deposits becoming non-refundable so you can get them back if you decide not to proceed.

Site Selection and Due Diligence

Looking for sites • Immerse yourself in the community, drive it, bike it, walk it, understand it. • Meet with community groups • Map it: Google maps, parcel map services • Immerse yourself in the market: Internet data, visit projects, talk to tenants.

Site Selection and Due Diligence

Looking for sites (continued) • • • •

Talk to city hall Attend city council meetings Understand the entitlement process. Develop relationships with brokers, but recognize that brokers have only a part of the market.

Site Selection and Due Diligence

Decide what the site is worth • Organize your analysis around the six focus areas. • Identify the areas of uncertainty and do more research. • Exercise judgment about market, construction and entitlement risk.

Site Selection and Due Diligence

Begin negotiations • Find out about the owner. • Obtain as much information as possible from the owner during negotiations. • Understand before proposing. • Use the open book, where possible • Be trustworthy: never, never promise something you can’t do. • Recognize that buying land is a relationship. Site Selection and Due Diligence

Making the offer • A clear succinct letter of intent (LOI) or offer sets forth the major business terms. • Ask for concurrence on the letter as prerequisite to the attorneys negotiating the purchase contract. • Provide a reasonable time to execute the contract.

Site Selection and Due Diligence

The purchase contract • The property is “tied up”. • Now you can spend money on investigation (due diligence). • Insure that there is adequate due diligence time. Try to get as long as possible. • Refundable deposit during due diligence. • Minimize amount of non-refundable deposits prior to close of escrow. Site Selection and Due Diligence

The purchase contract (continued) • Focus on buyer’s conditions to close: – Condition of title and buyer’s obligations to deliver clear title. – Environmental and soils – Conditioned on receiving entitlement? – Maximum period to meet conditions – Deposit refund conditions

Site Selection and Due Diligence

Due Diligence • Engage your development team on the six areas of focus and pay them to get more reliable information. • Decide impact of more reliable info on contract price. • Decide whether to – proceed, – renegotiate, or – abandon.

Site Selection and Due Diligence

Typical due diligence cost: first 60-120 days (