PRICE BID - Gujarat Electricity Board

99 downloads 403 Views 208KB Size Report
10 Sep 2012 ... Subject. Supply of ISI marked Split air conditioner of 1.5 Ton Capacity of Standard reputed make (MITSUBISI, DINKINE ,HITACHI BLUE STAR,.
GUJARAT ENERGY TRANSMISSION CORPORATION LIMITED TRANSMISSION CIRCLE OFFICE, GONDAL.

PRICE BID Subject Supply of ISI marked Split air conditioner of 1.5 Ton Capacity of Standard reputed make (MITSUBISI, DINKINE ,HITACHI BLUE STAR, LG,ELECTROLUX) at 220 Kv Gondal and 132 Kv Jasdan S.S. Gondal. TENDER ISSUE TO : M/S

___________________________ ___________________________ ___________________________ ___________________________ ___________________________

GUJARAT ENERGY TRANSMISSION CORPORATION LIMITED TRANSMISSION CIRCLE OFFICE, GONDAL

Tender for Supply of ISI marked Split air conditioner of 1.5 Ton Capacity of Standard reputed make (MITSUBISI, DINKINE ,HITACHI BLUE STAR, LG,ELECTROLUX) at 220 Kv Gondal and 132 Kv Jasdan S.S. Gondal.

(1) Estimated cost (2) Earnest money (3) Last date of receipt of Tender

:::-

(4) Date of opening the tender

:-

(5) Price of Tender (6) Time limit

::-

Rs. 1,50,000.00 Rs. 1500.00 ____10.09.12 10.09.12

up to 13:00 Hrs. 16:00 Hrs.

Rs. 150.00 1 Month

EMD and Tender fee should be paid in D.D. in favour of Gujarat Energy Transmission Corporation Ltd. Superintending Engineer (TR) GETCO, C.O., Gondal Tender fee paid vide E.M.D. paid vide

M.R. No. ___________ Date : ___________ M.R. No. ___________ Date : ___________

Superintending Engineer (TR), Gondal. _______________________________________________________________________ I have read all terms and conditions of contract and abide by same in all respect. Date :- ____________ SEAL AND SIGNATURE OF CONTRACTOR / SUPPLIER.

GUJARAT ENERGY TRANSMISSION CORPORATION LIMITED TRANSMISSION CIRCLE OFFICE, GONDAL.

SCHEDULE-B Sr. No. 1

Description Supply of ISI marked Split air conditioner of 1.5 Ton Capacity of Standard reputed make (MITSUBISI, DINKINE ,HITACHI BLUE STAR, LG,ELECTROLUX) at 220 Kv Gondal and 132 Kv Jasdan S.S. Gondal. The necessary supporting structure and other accessories required for installation shall be in scope of supply including installation at place as directed by EIC TOTAL AMOUNT RS. .

QTY.

UNIT

05

No

Unit Cost

Total Cost

05

Superintending Engineer (TR) GETCO, C.O., Gondal

Date :Place :-

___________________ (Signature of Contractor)

CONDITIONS :1

PRICE: Price quoted in our price bid are for delivery F.O.R. destination

2

Price should be inclusive of Tax and other charges.

3

Agency has to install all the A/c machines free of cost as per inst. Of E.I.C.

4

Transit Insurance: Prices shall be inclusive of transit insurance right up to site and 30 days thereafter.

5

Penalty: We agree to GETCO’S penalty clause as per clause no. 20 of additional general terms and conditions of this tender.

6

Guarantee : We agree with standard warranty given by company.

7

Import License: We do / do not require import license from the Board.

8

Tender shall be submitted by R.P.A.D./Speed post Only.

9

Validity: Our offer is valid for 180 days from the date of opening of technical bid.

10

The GETCO reserves the right to accept or reject this offer without assigning any reason whatsoever the GETCO’S decision will be final and binding to us.

11

CST No./GST No. & TIN No. is to be submitted with offer GETCO‘s TIN No. is 2419012398 Dtd. 29.09.2005 & CST No. is 24690102398 Dtd. 29.09.2005

Date :___________________ Signature of Contractor

Superintending Engineer (TR) GETCO, C.O., Gondal

TECHINICAL BID Subject Supply of ISI marked Split air conditioner of 1.5 Ton Capacity of Standard reputed make (MITSUBISI, DINKINE ,HITACHI BLUE STAR, LG,ELECTROLUX) at 220 Kv Gondal and 132 Kv Jasdan S.S. Gondal. TENDER ISSUE TO : M/S

___________________________ ___________________________ ___________________________ ___________________________ ___________________________

GUJARAT ENERGY TRANSMISSION CORPORATION LIMITED TRANSMISSION CIRCLE OFFICE, GONDAL.360311

Supply of ISI marked Split air conditioner of 1.5 Ton Capacity of Standard reputed make (MITSUBISI, DINKINE ,HITACHI BLUE STAR, LG,ELECTROLUX) at 220 Kv Gondal and 132 Kv Jasdan S.S. Gondal. . (1) Estimated cost

:-

Rs. 1,50,000.00

(2) Earnest money

:-

Rs. 1500.00

(3) Last date of receipt of Tenders

:-

up to 13:00 Hrs.

(4) Date of opening the tender

:-

at 16:00 Hrs (if possible)

(5) Tender fee

:-

Rs.150.00

(6) Time limit

:-

1 Month

The Supplier / Manufacturer will have to submit their offer in two BID, (1) Technical BID and (2) Price BID. The main envelop will contain two separated covers i.e. Technical BID and Price BID. The Technical BID shall be opened at 16:00 Hrs. if possible on due date. After scrutinizing the Technical BID, if party fails to fulfill the qualifying requirement, the Price BID of such parties will not be opened. The Price BID of qualifying parties, thereafter shall be opened on the Dt. & Time communicated to qualified parties in the presence of parties attending the price bid opening The BID should be clearly super scribed with our reference No. Due Dt. & title of work etc.

SEAL AND SIGNATURE OF CONTRACTOR / SUPPLIER. CONDITIONS :-

Superintending Engineer (TR) GETCO, Gondal.

1. The product should have minimum warrantee period of 1 years. More warrantee period will be preferable and shall be given due weight age & preference. 2. The payment shall be made after satisfactory installation. 3. The above supply & installation is to be carried out at 220 kv S/SGondal and 132 kv S/S Jasdan 4. The party has to arrange for transportation of man & material to site of work at his own cost. 5. No price escalation will be paid. Rate quoted should be firm up to the period of contract. 6. If found necessary, the order may be awarded to more than one agency against the tender. 7. The work of installation shall be carried out through experienced & conversant technician only. 8. In price BID, Only unit rate should be shown including of all taxes & other charges if any, break up of which is to be given. 9. The party has to provide service after sale for 1 year without charging any extra cost.

SEAL AND SIGNATURE OF CONTRACTOR/SUPPLIER

Superintending Engineer (TR) GETCO, C.O., Gondal

GUJARAT ENERGY TRANSMISSION CORPORATION LIMITED TRANSMISSION CIRCLE OFFICE, GONDAL

SPECIAL INSTRUCTIONS TO TENDERERS 1.

The tender should be submitted in original. On cover, it should be distinctly indicated as “Bid against Tender Notice No TCG- _________________Technical and Price bid filled and sealed in to two separate covers marked ”Price Bid” & “Technical Bid”. The same should be put in separate sealed envelope and marked as above.

2.

The tenders may be sent by Registered Post / Speed Post only as to reach this office on or before___________ up to 14:00 hours. Due care should be taken to see that the tenders sent by post are posted well in advance to ensure the delivery by the prescribed date or even earlier. Tenders which are received late after due date of receipt, will not be considered.

3.

The tenderer who offers the lowest in percentage ( % ) i.e. lowest total amount will be awarded / recommended for placement of order. Item wise lowest % / value will not be considered for placement of order.

4.

Failure to furnish full and complete details or furnishing vague information will make the tender liable for rejection. The tenderer is at full liberty to give information about his capacity and establishment to execute the work / contract.

5.

The offer should be valid for a minimum period of 180 days from the date of opening of Tender.

6.

The Technical Bid shall be opened on ___________at 16:00 hours in the office of Superintending Engineer(Tr.), GUJARAT ENERGY TRANSMISSION CORPORATION LTD, Transmission Circle, Gondal (if possible).

7.

The offer is liable to be out rightly rejected in case the “ Price Bid” and “Technical Bid” are not submitted separately as specified.

Sealed and Signature of Contractor/Supplier

Superintending Engineer (TR) GETCO, C.O., GONDAL

GUJARAT ENERGY TRANSMISSION CORPORATION LIMITED TRANSMISSION CIRCLE OFFICE, GONDAL

TECHNICAL SPECIFICATION The Split Air conditioner Machine should have following function. 1. 2. 3. 4. 5. 6. 7. 8. 9.

Sleep function ON / OFF Timer Anti bacteria filter Turbo Speed Energy Saving Memory backup operation Cool / Dry operation Auto cool.

10. The literature of the A/C M/C are to be used by the contractor must be enclosed with the tender .Without the literature the offer will not be accepted. 11. The contractor shall offer 1 year warranty after commissioning there against defective design and for material and for bad workmanship etc. Bidder offering more warranty period shall be preferred. 12. The A/C M/C offered should have satisfactory working performance in Indian atmospheric condition. 13. At the time of supply , it should be as per the order and with original company (Manufacturer’s) packing only, having manufacturer’s logo / Mark embossed / printed (not the sticker) with batch No. 14. Tender forms will be issued to those contractor who is company’s authorized sales & services .person and also completed such type of work

Sealed and Signature of Contractor/Supplier

Superintending Engineer (TR) GETCO, C.O., Gondal

GUJARAT ENERGY TRANSMISSION CORPORATION LIMITED TRANSMISSION CIRCLE OFFICE, GONDAL

Additional General Terms and conditions: 1.

Contractor will have to make his own arrangement for all tools, tackles, manpower etc.

2.

No tools, tackles, manpower will be provided by the GETCO.

3.

Contractor will be fully and solely responsible for any shortage, damage, materials / equipments while executing the work.

4.

The cost of damages, shortages, breakages will be recovered from the contractor’s bill. The assessment of which will be done by Engineer at his sole discretion and his decision shall be binding to the contractor and shall be considered as final and unchallengeable.

5.

The GETCO will not be responsible for any accident, injury etc. to the Contractor’s Labour or any disability to those persons while execution of the job. Any shortages / loss / damage to Contractor’s equipments / tools-tackles during execution of work will be liability of the contractor.

6.

Contractor will have to give indemnity bond to GETCO against any possible claim of compensation for damage to GETCO equipments or staff or any other third party during the execution of whole job. If for any reason, GETCO is called up on to pay any such claim or compensation, the same will be recovered from the contractor’s bill any where pending with GETCO even at any later date.

7.

For attending the work by contractor will be informed in advance, so as to keep ready skilled labourer, tools, tackles and other require materials. The GETCO will not be in any case responsible for any delay in completing the job. No. extra charge for any matter, whatsoever will be paid to the contractor. If contractor fails to execute the job in reasonable time, the job will be done at contractors risk and cost. Penalty/additional expenditure as per GETCO rules will be levied and will be recovered from the contractors running bills/deposit etc. will be forfeited, reserving all rights of the GETCO to recover from balanced dues.

8.

Contractor or his authorized representative should constantly remain present while executing complete job to avoid any complication.

9.

Contractor must engage sufficient skilled labors and competent experienced supervisory staff for executing the job, so as to avoid unnecessary delay, to complete the timely and as per requirement of order.

10.

Contractor will have to complete entire job as per instruction, if fails, to do so, entire work will be carried out at contractor’s risk and cost.

11.

A Solvency Certificate to the extent of 20% of ordered value will have to be produced by the contractor.

leakages to any

12.

Contractor will abide by and fulfill all the terms and conditions and general terms & conditions of the contract for works as prescribed by GETCO.

13.

Contractor will be solely and fully responsible for any accident, damage either to private or public properties or any human being during execution of the entire job.

14.

Other general terms and conditions as prevailing in the GETCO will also apply to these jobs.

15.

In case of any dispute or doubt, the decision of Superintending Engineer(TR), Gondal shall be final and binding to the contractor.

16.

The GETCO reserves the right to terminate this contract at any time during its tendency without giving notice of termination or any reason thereof.

17.

If the contractor will fail to arrange to execute the job in time and due to this any revenue loss occurs, the same will be recovered from the contractor.

18.

The GETCO shall deduct the any other levy or duty as per Government Law/prevailing rules from each & every bill.

19.

Any dispute arising out of this tender documents will be subject to Gondal jurisdiction.

20.

If the work is not completed in time after issue of order, the contractor shall be liable to pay penalty up to ½% per week of the total amount subject to maximum of 10% recovered on the contract value.

21.

Contractor has to submit last I.T. clearance certificate and necessary documents of experience.

SEAL AND SIGNATURE OF CONTRACTOR/SUPPLIER

Superintending Engineer (TR) GETCO, C.O., GONDAL